Manufacturing examples
One shortage affecting five customer orders
How a two-day delay on one granule grade spread through the week.
The chain
- Supplier delays PP granules by two days
- Two moulding jobs cannot start
- Planning moves other jobs forward
- Five customer orders shift by one to three days
- One customer holds payment until delivery
What would have helped
A morning days-of-cover check would have shown the risk four days earlier.