Plan-to-deliver: daily operating review pack
This pack is the sheet a planner and shift supervisor carry into the daily huddle. It compares yesterday's plan with what actually happened, sets out today's capacity, and records the decisions that shape tomorrow. Operations managers in factories, workshops and service businesses use it to keep the day's work realistic and visible to everyone on the floor.
When to use it
Hold the huddle at the start of each shift or working day and keep it short, about fifteen minutes, standing. Bring the figures on paper or on a shared sheet so that the discussion is about decisions, not about finding numbers.
The template
| Agenda item | Figure to bring | Source record | Decision | Owner | Due |
|---|---|---|---|---|---|
| Actions carried over from the last huddle | List with original dates | Huddle decisions | Close, extend or escalate each one | Shift supervisor | |
| Yesterday's plan against actual output | Planned quantity, actual quantity, gap | Daily plan | Which gaps need action today | Planner | |
| Reasons for slippage | One reason per gap, such as late material or breakdown | Progress notes | Who removes each cause | Planner | |
| Today's people and free capacity | People present, absent, hours available | Attendance, capacity board | Reallocate work or arrange cover | Shift supervisor | |
| Equipment and material readiness | Machines down, material short, planned maintenance | Capacity board | What to hold, move or arrange | Operations manager | |
| Rush or changed orders | Order, quantity, new date | Demand forecast | Accept, refuse or reschedule with the customer | Operations manager | |
| Load for the next two days | Hours required against hours free | Capacity board, daily plan | Whether tomorrow's plan is achievable | Planner |
How to fill it
- Figure to bring: a number the supervisor can speak to in one sentence. Prepare it before the huddle.
- Source record: write down where the number came from so it can be checked later.
- Decision: write the actual decision taken, such as "move job 7 to Thursday", not "discussed".
- Owner and Due: a named person and a time. If the decision involves overtime or extra hours, check the current rule on the official portal or with your CA before acting.
- Actions carried over: keep the first date, so you can see how long something has been open.
Example row
| Agenda item | Figure to bring | Decision | Owner | Due |
|---|---|---|---|---|
| Yesterday's plan against actual output | Planned 420 units, made 360, gap 60 units, about ₹27,000 at selling price | Press 2 breakdown caused 45 of the gap. Move 60 units to tomorrow's first shift | Planner | 9:30 today |
Review and sign-off
- The shift supervisor runs the huddle and the operations manager initials the sheet at the end of the day.
- Every day, the sheet is reviewed in the huddle. Each week, the manager looks across the sheets for gaps that repeat.
- Escalate to the owner when a promised customer date will be missed because of a gap that the huddle could not close.
Keeping up to date
- File each day's sheet in date order and keep them for the period your CA or the law requires.
- Change the agenda when you learn which items never produce decisions, and add items where problems keep surprising you.
- Carry unfinished actions to the next sheet instead of rewriting them, so that ageing items stay in view.