Cavity count

Cavity count is the number of part-forming impressions in a mould, which determines how many parts are produced in each cycle.

What it means

A one-cavity mould makes one part per cycle, a four-cavity mould four. More cavities raise output but cost more to build, need a bigger machine and make balance and maintenance harder. The cavity count is chosen from the order volume, part size, machine size and budget. It is also used in the output formula, where pieces per hour equal cavities times cycles per hour.

Example

A buyer needs 600,000 spice jar lids a year. With a 30-second cycle on a 2-cavity mould, the plant makes 240 lids an hour, which is about 1.9 million a year over 8,000 hours. Both numbers cover the demand, so the cheaper 2-cavity mould is chosen over a 4-cavity one.

Records and checks

  • Record the mould ID, number of cavities, the number of cavities active and any blocked cavity.
  • Verify the active cavity count before each run, since output and rejection rates depend on it.
  • The moulding supervisor confirms at setup, and the planner uses the same figure when estimating run time.

Common mistakes

  • Running with a cavity blocked off but using the full count to report output.
  • Choosing a high cavity count for a small order, and paying for a mould it will never fill.