Change order

A change order is a formal, written change to the scope, quantity, specification, price or delivery date of an order or contract that is already in force, agreed by both parties.

What it means

In job work and project businesses, customers often alter details after confirming an order. A change order records the new terms and the effect on price and time, before the work is done. Without it, the supplier does the extra work unpaid, or the customer disputes the final bill. Each change should be numbered and approved.

Example

A contractor is building 20 steel gates at ₹14,000 each. The buyer asks for an added mesh panel on each. The contractor issues change order 1, adding ₹2,500 per gate and 5 days, and starts the work only after the buyer signs it.

Records and checks

  • Record the order number, the change requested, price and time effect, the date and who requested it.
  • Verify that the change has been signed by the customer and passed to the shop floor.
  • The sales manager raises it, the customer approves it, and the production planner confirms the new date.

Common mistakes

  • Accepting a change by phone and doing the work with nothing in writing.
  • Updating the shop floor drawing but leaving the sales order and price unchanged.