Contract demand
Contract demand is the maximum electrical demand, usually in kVA, that an industrial or commercial consumer agrees with the utility to draw on its connection.
What it means
It is set in the supply agreement and decides fixed charges and the point at which penalties apply. Setting it too high means paying fixed charges for unused capacity. Setting it too low risks going past it during a busy period and being billed extra for the excess. Firms review it after adding machines or improving power factor.
Example
A foundry in Rajkot has a contract demand of 250 kVA but its recorded peaks average 170 kVA. After a year of readings it applies to reduce it to 200 kVA, cutting fixed charges while leaving a safety margin.
Records and checks
- Record contract demand, the monthly recorded maximum demand and any excess billed.
- Verify the bill against the supply agreement and meter readings each month.
- The electrical head proposes any change and the owner approves it before the application.
Common mistakes
- Never reviewing the figure after machines are added or removed.
- Paying excess demand penalties month after month without checking the cause.
Check the current rule on the official portal or with your CA before acting.