Cost comparison
Cost comparison is the evaluation of the total cost of alternative purchasing options, including freight, quality losses, handling and payment terms, not only the quoted price.
What it means
A low price can hide costs elsewhere: higher rejections, long transport, minimum order quantities that fill the store, or short credit. A cost comparison adds all of these to give a figure per usable unit for each option. It is used to choose between suppliers, materials or between making and buying a part. The decision should be based on the full cost, together with risks that cannot be priced.
Example
A Rajkot casting buyer compares two foundries for a housing. Foundry A quotes ₹210 per piece, with 6 per cent rejection and ₹12 freight. Foundry B quotes ₹225, with 1 per cent rejection and ₹6 freight. Cost per good piece is about ₹236 for A and ₹233.5 for B, so B is cheaper in practice.
Records and checks
- Record price, freight, rejection rate, handling, credit period and any one-time costs for each option.
- Verify rejection and delay figures from actual receipt records, not the vendor's promise.
- The buyer prepares it; the purchase head reviews it and the quality head confirms the rejection data.
Common mistakes
- Using the quoted rejection rate from the vendor instead of the measured figure.
- Ignoring the cost of capital tied up when comparing a large minimum order with a small one.