Critical path
The critical path is the longest sequence of dependent tasks in a project; a delay in any of them pushes back the project's finish date.
What it means
Where CPM is the method, the critical path is its result: the specific list of tasks that cannot slip. It shows what to protect, with extra labour, materials ready in advance or tighter supervision. It can change during the job: if a non-critical task slips far enough, it becomes critical. Recheck it whenever the plan changes.
Example
A contractor building a small factory shed finds the critical path is excavation, footing, columns, roof steel and roofing. When the steel supplier is late by a week, the handover date moves a week. A delay in painting would not.
Records and checks
- Record: the tasks on the path, planned and forecast dates, float on near-critical tasks and the owner of each.
- Verify: that long-lead items on the path, such as steel or machines, have confirmed delivery dates.
- Checked by: the project manager reviews the path weekly at the site meeting.
Common mistakes
- Chasing every task equally rather than the ones on the path.
- Assuming the path from the first plan is still valid after changes.