Critical spare

A critical spare is a part, often costly or slow to obtain, that is kept in stock because its failure would stop an important machine for a long time.

What it means

You cannot stock every spare, so you choose the ones that hurt most when missing. A part qualifies when its failure halts production, the machine has no standby, and the supplier needs weeks to deliver. Common examples are motors, control cards, special bearings and imported gears. Keeping them costs money and space, so owners balance the cost of holding against the loss from waiting.

Example

A plastics unit keeps a spare screw barrel worth ₹1,80,000 for its main moulding machine. Lead time from the maker is six weeks, and a stoppage costs about ₹60,000 a day, so the spare is justified.

Records and checks

  • Record the part number, machine, quantity held, supplier, lead time and storage location.
  • Verify the spare physically exists, is protected from rust and damp, and fits the machine.
  • The maintenance in-charge decides the list; the storekeeper counts it, and the owner approves the investment.

Common mistakes

  • Using the critical spare for routine repairs and not replacing it.
  • Listing parts by cost alone, not by the impact of their absence.