CRP

CRP is the common abbreviation for capacity requirements planning, the check of whether planned production can be done within the available machine and labour hours.

What it means

Planners run it after the material plan produces a list of orders for the coming weeks. It shows, for each machine group, the hours demanded week by week against the hours on offer. Peaks show as overloads and gaps as spare time. The planner can then shift orders earlier, split lots, add overtime or send work out, before the problem arrives on the shop floor as late deliveries.

Example

At a Hosur fastener plant, the weekly CRP shows thread rolling at 118 per cent of capacity in week 3 and 62 per cent in week 4. The planner brings forward two orders into week 4 and tells sales that a third will ship on Monday instead of Friday, rather than discovering the overload on Thursday.

Records and checks

  • Record the weekly load and capacity for each work centre, and any change made.
  • Verify that the plan is rerun after each major order change and not only at month start.
  • The production planner runs it; the plant manager approves overtime or outsourcing decisions.

Common mistakes

  • Looking at monthly totals, where a heavy week and a light week average out and hide the overload.
  • Running it once and never updating it when new urgent orders arrive.