Cutting list

A cutting list is a table of every part to be cut for a job, with its material, dimensions and quantity, used to order stock and instruct the cutting team.

What it means

It is usually prepared from the fabrication drawing before the job starts. Each row names the item, section or plate size, length, quantity and sometimes the cutting method. Planners group the rows to choose stock lengths and reduce offcuts.

Example

A structural fabricator preparing a platform frame lists 12 angles at 1,450 mm, 8 at 900 mm and 6 at 600 mm in 50 x 50 x 5 angle. By combining lengths from 6-metre bars, it buys 9 bars and keeps offcuts under 300 mm.

Records and checks

  • Record the job number, drawing revision, part marks, sizes, quantities and the stock lengths allocated.
  • Verify the list against the drawing and the bill of material before any cutting begins.
  • The draughtsman prepares it, the production engineer checks it, and the store issues material against it.

Common mistakes

  • Using an old drawing revision, so the whole batch is cut to the wrong length.
  • Leaving out spare quantity for rejects and trial pieces on critical parts.