Cutting plan
A cutting plan sets how an order will be cut: the number of lays, the marker for each, the plies and the quantity of each size and colour.
What it means
Orders arrive as quantities by size and colour, and the plan turns them into lays that fit the cutting table and fabric rolls. Planners balance the number of plies, marker length and the size ratio to deliver the exact order plus any allowed excess with low fabric waste. A good plan also allows for fabric defects and end losses.
Example
For 2,400 trousers in sizes 30 to 38, the planner makes 5 lays of 80 plies each with a 1:2:2:1 ratio. The plan shows 4 percent end loss and a fabric need of 3,360 metres, so purchase orders the right amount.
Records and checks
- Record lays, markers, plies, ratios, fabric required and expected output.
- Verify the plan's total pieces against the order for each size.
- The cutting head prepares it; merchandising approves it before fabric is issued.
Common mistakes
- Ignoring fabric width differences between rolls, which makes markers too long.
- Overcutting a size without approval, creating unwanted stock.