Design freeze
A design freeze is the stated point after which a product's design is locked, and any further change needs a formal request and approval.
What it means
Design work can go on forever if nobody draws a line. The freeze marks the date when drawings and specifications are considered final enough to order tooling, buy materials and plan production. Changes are still possible afterwards, but they go through a controlled process that counts the cost and delay. The freeze protects the production team from a moving target.
Example
A manufacturer of school furniture in Indore freezes the design of a new desk on 10 June, before ordering a ₹4.5 lakh press tool. A week later the owner suggests rounded corners. Since this would change the tool, it goes through a change request, which adds ₹38,000 and two weeks, and is declined for this season.
Records and checks
- Record the freeze date, the revision of drawings frozen and who agreed to it.
- Verify that all drawings and the parts list carry the frozen revision before tooling orders go out.
- The product lead declares the freeze; the owner approves any exception.
Common mistakes
- Announcing a freeze but quietly allowing small changes, so nobody trusts the drawings.
- Freezing too early, before testing, so serious flaws surface after the tool is already made.