Finite capacity scheduling
Finite capacity scheduling is the sequencing of jobs on each machine or work centre within the hours it can actually provide, so that promised dates are achievable.
What it means
Simple planning assigns jobs to dates without asking whether the machine is free. Finite scheduling treats each machine's hours as a hard limit. A job that does not fit waits, moves to another machine or pushes lower-priority work out. The result is a schedule with start and finish times that can be followed, which in turn gives more honest delivery promises to customers.
Example
A Coimbatore foundry has one 4-tonne induction furnace that can pour 6 heats a day. Eight heats are requested for Tuesday. The scheduler fits the six most urgent, shifts two to Wednesday morning, and tells sales that the two affected customers will receive goods a day later than they hoped.
Records and checks
- Record each machine's available hours, the jobs sequenced, start and finish times and priorities.
- Verify that setups, maintenance windows and shift patterns are included in the available hours.
- The planner builds it; the production head approves priority conflicts and informs sales of changes.
Common mistakes
- Loading a machine to 100 per cent of its hours, leaving no room for breakdowns or urgent jobs.
- Not refreshing the schedule when a job runs late, so the plan gradually becomes fiction.