First time right
First time right is the percentage of jobs, parts or transactions done correctly at the first attempt, with no rework, correction or repeat.
What it means
It measures quality at the point of work, not at the end. A job that passes inspection after being reworked does not count as right first time. A high figure means less rework, less waste and quicker delivery. It is also used in service work, where a repeat visit to fix the same fault counts as a miss.
Example
A machine shop makes 500 housings in a month. Of these, 455 pass final inspection without any rework, and 45 were corrected or scrapped. First time right is 91 percent. Each rework costs about ₹120, so the 45 corrections cost roughly ₹5,400.
Records and checks
- Record the total units, units passing first time, units reworked or scrapped and the reason for each.
- Verify that reworked units are not quietly counted as first-time passes.
- The inspector logs each result, and the production head reviews causes of failure weekly.
Common mistakes
- Counting a unit as right first time after an operator fixes it before inspection.
- Measuring only final inspection and missing rework done midway through the process.