Gantt chart
A Gantt chart is a bar chart that shows a project's tasks down the page and time across it, so each bar shows when a task starts, how long it lasts and what overlaps.
What it means
It lets everyone see the whole plan at a glance: what is happening this week, what comes next and which tasks run in parallel. Links between bars show dependencies. A Gantt chart presents a schedule; it does not itself calculate the critical path, though the schedule behind it can. It is easy to read, which is why it is used in site meetings and with clients.
Example
For a 90-day warehouse build, one bar runs from day 1 to day 15 for excavation, the next from day 12 to day 40 for foundations and columns, and so on. At the review, the manager sees that roofing starts the same week monsoon is forecast and shifts it.
Records and checks
- Record: task, start, finish, duration, links, percentage done and the baseline dates for comparison.
- Verify: that bars reflect actual progress each week and not only the original plan.
- Checked by: the planner updates it; the project manager reviews slipping tasks in the weekly meeting.
Common mistakes
- Printing the chart once and never updating it.
- Drawing bars without links, so a delay in one task does not show its effect on others.