Incident closure

Incident closure is the formal point at which an incident's investigation is complete, every corrective action is done and verified, and the record is signed off.

What it means

An incident is not finished when the injured person returns or the machine restarts. It is finished when the root cause is identified, each corrective and preventive action has an owner and has been completed, and someone senior has confirmed the fix works. Until then the file stays open.

Example

A packaging unit in Pune removes a conveyor guard after a worker's sleeve is caught, causing a minor injury. The file closes only after a fixed guard is bolted on, the ₹4,200 repair bill is booked, and the supervisor re-checks it a week later.

Records and checks

  • Record the root cause, each action, its owner, due date and completion date.
  • Verify on site that the fix is in place and still working, not only reported as done.
  • The plant head or safety officer signs the closure; the person who did the work should not close their own action.

Common mistakes

  • Closing the file because the injured worker is back, while corrective actions are still open.
  • Ticking actions as done on paper without anyone looking at the shop floor.