Infinite capacity planning
Infinite capacity planning is a way of scheduling jobs by due dates and lead times alone, assuming machines can take any load, and then checking overloads afterwards.
What it means
It calculates when each job should start in order to finish by its due date, without considering whether the machines have the hours. The planner then looks at the load report to see where machines are over-booked, and resolves it by adding shifts, outsourcing or moving dates. It is simple and quick, and suited to firms with ample spare capacity, but it can create schedules that cannot be followed if the shop is busy.
Example
A Noida garment exporter schedules 14 orders by ship date. The first plan puts 5,200 pieces on the sewing line in week 2, though its capacity is 3,600. The planner sees the overload on the report and sends 1,000 pieces to a contractor and moves 600 to week 3.
Records and checks
- Record the planned start and finish dates, and the load per work centre against capacity.
- Verify the overload report each week and record what action was taken for each excess.
- The planner prepares it; the production head decides on overtime, subcontracting or date changes.
Common mistakes
- Treating the first schedule as final, without reading the overload report.
- Using it during peak season when every machine is full, so it fails to give workable dates.