Machine utilisation
Machine utilisation is the percentage of a machine's available time during which it is actually running, calculated as running hours divided by available hours.
What it means
It shows how well an expensive asset is used. Available hours are the planned working hours; running hours are what remains after setup, breakdown, waiting and idle time. Low utilisation means money sitting idle, while very high utilisation may leave no room for maintenance. It counts time only and says nothing about speed or quality.
Example
A shop plans 200 hours on a lathe in a month. Breakdowns take 20 hours, setups 25 and waiting for material 35. Running time is 120 hours, so utilisation is 60 per cent, and waiting for material is the biggest loss.
Records and checks
- Record planned hours and each loss category by machine, such as setup, breakdown and waiting.
- Verify that the available hours used are consistent from month to month.
- The production manager reviews it weekly; maintenance and stores act on the losses assigned to them.
Common mistakes
- Using a 24-hour day as the base for a machine that works one shift, which makes every figure look poor.
- Pushing utilisation up by running low-value jobs while profitable orders wait.