Maintenance backlog
Maintenance backlog is the set of approved maintenance jobs that have been raised but not yet completed, usually measured in number of jobs or hours of work.
What it means
Every plant has some pending work. The concern is a backlog that keeps growing, as it signals too few people, shortage of spares or poor planning. A common measure is backlog hours divided by weekly technician hours, which shows how many weeks the team would need to clear it. Old, unresolved jobs often hide safety problems and later turn into breakdowns.
Example
A factory has 48 open jobs totalling 180 hours. Its three technicians have 90 hours a week for planned work, so the backlog equals two weeks, and 9 of the jobs are over 30 days old.
Records and checks
- Record each open job with date raised, priority, estimated hours and reason it is pending.
- Verify the list weekly and close jobs that were done but not updated.
- The maintenance supervisor maintains the list; the owner reviews old and high-priority items.
Common mistakes
- Never closing completed jobs, which makes the backlog look larger than it is.
- Leaving jobs waiting for spares with no purchase request raised.