Minimum purchase commitment

A minimum purchase commitment is a buyer's agreement to purchase at least a stated quantity or value from a supplier in a period, usually in exchange for better pricing or supply assurance.

What it means

Suppliers can plan production and offer lower prices if they know a base volume is sure. In return, the buyer promises to purchase at least that much, and the contract may state a charge or lost discount if the buyer falls short. For the buyer, the risk is demand falling below the commitment, leaving stock to be absorbed or a shortfall payment. It should be set against a conservative forecast.

Example

A Vapi chemical buyer agrees to a yearly minimum of 120 tonnes of a solvent at ₹92 per kg, against a market price of ₹98. By the ninth month, it has bought 70 tonnes, and demand is soft. The buyer asks to spread the rest over the next six months to avoid a shortfall charge.

Records and checks

  • Record the commitment amount, period, price, shortfall terms and the quantity bought to date.
  • Verify progress against the commitment monthly, with a forecast of the likely year-end position.
  • The purchase head tracks it; the owner approves the commitment before signing.

Common mistakes

  • Committing to a volume based on the best-case forecast rather than a cautious one.
  • Not tracking progress, so the shortfall is discovered only when the supplier invoices it.