Minimum stock level
Minimum stock level is the lowest balance you are prepared to see for an item, below which production or sales are at risk of stopping.
What it means
It is the floor, and in practice it equals the buffer you want left even if a delivery is late. A usual working is reorder level minus normal usage during the normal lead time. Falling below it signals that an order was late, a supplier delayed or use rose. It should trigger urgent action, not routine reordering.
Example
A plastic moulder uses 50 kg of granules a day and normally waits 6 days for delivery. Reorder level is 400 kg, so minimum level is 400 minus 300, which is 100 kg. At 90 kg, the supervisor calls the supplier the same day.
Records and checks
- Record the minimum level per item and each time stock falls below it, with the cause.
- Verify the figure whenever the supplier's lead time changes.
- The stores in-charge reports breaches; the purchase head follows up with the supplier.
Common mistakes
- Confusing it with the reorder level, so orders are placed only when the floor is already reached.
- Ignoring repeated breaches instead of changing the supplier, lead time assumption or buffer.