Mould setting

Mould setting is the work of mounting a mould on the machine and adjusting clamp, ejection, cooling and process values until it makes approved parts.

What it means

Changing from one job to another means removing one mould, fitting the next, connecting water and any hydraulics, setting strokes and then proving the process. The time between the last good part of the old job and the first good part of the new one is the changeover time. Quick, repeatable settings, written on a setup sheet, cut this time and reduce the number of trial rejects.

Example

A moulder switches from a bottle cap job to a tray job at 2 pm. The setter fits the mould, hooks up water, loads the saved settings and runs trial shots. The first approved part comes at 3.45 pm, so the changeover costs 1 hour 45 minutes, down from over 3 hours before the setup sheets were used.

Records and checks

  • Record the mould and machine, changeover start and end times, settings used and the number of trial parts.
  • Verify the first article against the drawing and the previous approved setup before releasing production.
  • The setter performs and records the change, the quality inspector approves the first article, and the supervisor reviews changeover times.

Common mistakes

  • Not recording final settings, so the next job starts from guesswork again.
  • Releasing the run before the first article is approved by quality.