Moulding cycle

The moulding cycle is the complete sequence of steps for one shot, from mould closing and injection through cooling to opening and ejection of the parts.

What it means

Each cycle includes mould close, injection, hold, cooling and plasticising, mould open, ejection and any robot or operator removal. Cooling is usually the longest step. Cycle time decides the output per hour, since a shorter cycle makes more shots, and it feeds directly into the cost per part through machine rate and labour. Small savings of a second or two add up over a long run.

Example

A 6-cavity cap mould runs a 15-second cycle, so it makes 240 shots an hour and 1,440 caps. The team cuts the cycle to 14 seconds by shortening the open time, and output rises to about 1,543 caps an hour, a gain of roughly 7 percent from a one-second saving.

Records and checks

  • Record the cycle time with its break-up into injection, hold, cooling and open and eject time, for each job.
  • Verify with a stopwatch or the machine counter that actual cycle matches the standard used in costing.
  • The setter records the settings, the supervisor reviews actual versus standard, and the planner updates the standard when it changes.

Common mistakes

  • Quoting a job on the best cycle time seen, not the average over a shift.
  • Cutting cooling to shorten the cycle and then seeing warpage later.