MPS
MPS is the abbreviation for master production schedule, the plan stating how many of each finished product will be completed in each period.
What it means
In planning meetings, the MPS is the figure everyone works toward: sales commits to it, purchasing buys for it and the shop floor builds to it. It is reviewed at a regular rhythm, perhaps weekly, with an early part that is firm and a later part that is open to change. It is usually set at the level of the items sold to customers, not at the level of every sub-assembly.
Example
At a Kolhapur foundry making pump casings, the MPS for next week reads 600 units of casing A, 350 of casing B and 150 of casing C. On Monday, a customer asks for 200 more of casing B. Planning checks the pattern and furnace hours, and replies that this can be added only from the week after.
Records and checks
- Record each item's weekly quantity, the revision date and the reasons for any change.
- Verify that firm quantities match confirmed orders and that total hours fit the available capacity.
- The planner maintains it; the plant head approves changes to the firm weeks.
Common mistakes
- Letting different departments keep their own versions, so purchase and production plan different quantities.
- Never closing out last week's gap, so unfinished quantities vanish from view.