MRP
MRP is the abbreviation for material requirements planning, the method of calculating what materials to order or make, in what quantity and by what date.
What it means
It is the backbone of planning in a factory that assembles or manufactures from many parts. The planner or system takes the schedule of finished products, breaks it into components using the parts list, subtracts stock and open orders, and offsets by lead time. It results in suggested purchase and production orders. Where there are few parts and little variety, a simple spreadsheet may do the same job.
Example
A Rajkot electric-motor maker plans 300 motors for next month. Each uses one rotor, one stator, 2 bearings and one terminal box. After deducting 80 stators and 140 bearings on hand, the run suggests making 220 stators, buying 460 bearings and placing the bearing order by the 5th due to its 3-week lead time.
Records and checks
- Record the demand, parts lists, stock levels, supplier lead times and suggested orders.
- Verify stock counts, and that the parts list revision used is current, before acting on the run.
- The planner runs it; purchasing approves and places orders, and stores confirms the stock figures.
Common mistakes
- Following the suggestion blindly when the underlying demand was a rough guess.
- Forgetting that scrap or rejection rates add to the real requirement.