Planned order

A planned order is a proposed quantity of an item to be made or bought by a certain date, suggested by planning, that has not yet been released as an actual order.

What it means

When planning finds a shortage ahead, it proposes an order that will cover it, with a quantity and a start date allowing for lead time. It is still a suggestion: no supplier has been told and no job has started. A planner reviews it and either converts it into a purchase or production order, changes it or lets it drop if demand changes. Because planned orders move with each run, they should not be treated as commitments.

Example

For a Nashik bakery equipment maker, planning suggests an order of 600 meters of stainless sheet by 20 July, due to a shortage in week 31. The purchaser checks and sees another order of 150 meters is already due. She converts a planned order of 450 meters to a purchase order with the supplier.

Records and checks

  • Record the item, quantity, need date, release date and the demand that created it.
  • Verify against current stock and open orders before converting any planned order.
  • The planner reviews daily or weekly; the purchase head authorises conversion to real orders.

Common mistakes

  • Telling a supplier a planned order is firm, then changing it and damaging the relationship.
  • Never reviewing them, so release dates pass and urgent orders are placed at higher cost.