Plasma cutting

Plasma cutting is a thermal process that uses a constricted electric arc and a fast gas stream to melt and blow away conductive metal along a cut line.

What it means

It works on mild steel, stainless steel and aluminium, and is quicker and cheaper than laser on plates from about 6 mm upward. The cut is wider than a laser cut, with a more angled edge and a larger heat affected zone, so precision parts may need finishing.

Example

A fabricator cuts 30 base plates of 20 mm mild steel on a CNC plasma table. Each plate takes about 3 minutes, and the cut edges need light grinding before welding. Sending the same job to a laser shop would cost more for this thickness.

Records and checks

  • Record the material, thickness, current setting, cutting speed, consumables used and the program file.
  • Verify the first part's dimensions and edge squareness against the drawing.
  • The operator replaces consumables on schedule, and the supervisor checks the first piece.

Common mistakes

  • Running worn nozzles and electrodes, which gives angled, rough cuts and oversized holes.
  • Using plasma for tight-tolerance parts without a machining allowance.