Production order

A production order is the authorised instruction to make a specific quantity of an item by a given date, listing the materials, operations and responsibilities.

What it means

It converts a plan into action. The order names the item, the quantity, the due date, the parts list and the route through the work centres. Stores uses it to issue materials, the shop floor uses it to schedule and report progress, and accounts uses it to collect costs. When complete, the order is closed with the actual quantity made, and any difference from the plan is noted.

Example

A Pune paint maker raises production order PO-3317 for 2,000 litres of white emulsion, due on 18 September. It lists pigment, resin and additives per batch of 500 litres, four mixing batches, and a quality check before filling. At close, 1,980 litres were filled, with 20 litres held back for retest.

Records and checks

  • Record the order number, item, quantity, dates, materials issued, quantity completed and scrap.
  • Verify that material issued matches the parts list, and that the quantity made is counted at closing.
  • The planner releases it; the supervisor confirms completion and the cost clerk closes it.

Common mistakes

  • Leaving orders open after completion, so work in progress looks bigger than it is.
  • Issuing material without an order number, so its cost cannot be traced to the job.