Rework order
A rework order is a separate job instruction to correct defective parts so that they meet specification, tracked with its own quantity, operations and cost.
What it means
When inspection finds parts that can be repaired rather than scrapped, the shop raises a rework order. It names the parts, the defect, the operations to repeat and who will do them. Keeping it apart from the original production order shows what poor quality really costs and stops good quantity and corrected quantity from being mixed up.
Example
A press shop in Pune finds 40 brackets out of 500 with oversize holes. It raises a rework order to bush and re-drill them, costing about ₹35 per piece in labour and tooling, and the corrected parts go back through final inspection.
Records and checks
- Record the defect reason, quantity, operations repeated, labour hours and any material added.
- Verify that reworked parts are inspected again against the original drawing before dispatch.
- The quality inspector signs off each order, and the production head reviews total rework cost every month.
Common mistakes
- Fixing parts quietly on the line without a rework order, so the cost and the defect never appear in any report.
- Mixing reworked pieces back into good stock before reinspection.