Routing
Routing is the defined sequence of operations, the work centre for each and the standard setup and run times, needed to make a product or component.
What it means
If the bill of materials is the recipe's ingredients, the routing is the method. It says first cut, then drill, then deburr, then heat treat, then inspect, with the machine or area for each step and the time expected. Planners use it to work out when each operation will occur and how many hours each machine will be needed. Costing uses its times to charge labour and machine cost to the product.
Example
For a hydraulic cylinder rod made in Coimbatore, the routing is: saw cut at 4 minutes, turning at 18, induction hardening at 6, grinding at 12, chrome plating sent out, inspection at 3. Planners add these up for 100 pieces to find about 72 hours of in-house work, and so can load each machine.
Records and checks
- Record each operation number, work centre, setup time, run time per piece and any inspection step.
- Verify the times by timing actual jobs and update the routing when methods or machines change.
- The process engineer owns it; planning and costing confirm that they use the same current routing.
Common mistakes
- Using standard times set years ago, so schedules and costs are wrong.
- Leaving outsourced steps out, so lead time is underestimated.