Running account bill

A running account bill is an interim bill raised during a contract for the value of work done so far, so the contractor is paid in stages rather than only at the end.

What it means

Building contracts last months, and contractors cannot carry the full cost until completion. Running bills, raised monthly or at set intervals, bring cash in as work advances. Each is built on measured quantities multiplied by contract rates, less earlier payments and agreed deductions such as retention, advance recovery and statutory deductions. A final bill closes the account.

Example

A contractor building a school block raises a running bill at the end of each month. In September, work measured is ₹9.6 lakh at contract rates. After earlier bills of ₹6 lakh and a 5 per cent retention on the total, the client certifies a net amount for payment.

Records and checks

  • Record: bill number, period, measurement book reference, work value, deductions and net amount certified.
  • Verify: that each quantity traces to a signed measurement and that rates agree with the contract.
  • Checked by: the site engineer measures; the accountant checks calculations; the client's engineer certifies.

Common mistakes

  • Raising the bill before measurements are agreed, which delays certification.
  • Mis-stating the cumulative figure so that earlier work is paid again.

Check the current rule on the official portal or with your CA before acting.