Scope of work

A scope of work is the written description of the work, deliverables, quantities and exclusions that a contractor or supplier agrees to carry out for a stated price.

What it means

It is the reference point for the quote, the contract and the final bill. A good one lists what is included, what is excluded, who supplies materials, the standard of finish and the handover condition.

Example

A small electrical contractor is hired to wire a 2,400 sq ft office floor. The scope names the number of points, the cable brand and gauge, the panel to be supplied, the testing to be done and states that false ceiling cutting is excluded. When the owner later asks for ceiling cutting, it is priced as an addition.

Records and checks

  • Record the scope as an annexure to the quote or work order, signed by both parties, with drawings or a bill of quantities.
  • Verify that quantities, brands, exclusions and handover conditions are specific enough to measure at completion.
  • The project head prepares it and the owner or client signs it before work begins.

Common mistakes

  • Writing vague lines such as "complete electrical work" with no quantities or exclusions.
  • Leaving out who arranges scaffolding, power, water and debris removal on site.