Setup time
Setup time is the time needed to prepare a machine or line for a new product, measured from the last good piece of the old job to the first good piece of the new one.
What it means
It covers removing old tooling, fitting new tooling, adjusting settings, loading material and making trial pieces until the output is acceptable. Long setups push owners towards big batches.
Example
A cable-lug manufacturer changes a press die three times a day. Each change takes 70 minutes, so over 3 hours of a 10-hour shift go on setup. Cutting each change to 40 minutes gives back 90 minutes of press time daily.
Records and checks
- Record the start and end time of every setup, the job it was for and the number of trial pieces scrapped.
- Verify that the time is stamped when the first good piece is approved, not when the machine merely starts.
- The shift supervisor checks entries daily, and the planner uses the average when scheduling jobs.
Common mistakes
- Using the machine manual's quoted setup time instead of the time actually taken on your floor.
- Counting trial pieces and waiting for the inspector as production time.
Did not find your answer?Message the lamp team on WhatsApp. Ask about setup, your records, or anything we have not covered here.Ask us on WhatsApp →