SMED

SMED is short for single minute exchange of dies, a lean method for reducing machine changeover time by doing as much preparation as possible while the machine is still running.

What it means

The team first films or times a real changeover, lists each step, and marks each as internal (machine must be stopped) or external (can be done earlier). External work is then moved ahead of the stop, and internal work is simplified with quick-fit fixtures and fixed stops.

Example

A bottle-cap line changes colour twice a day and loses 50 minutes each time. After a SMED exercise it keeps the next mould and hoses ready at the machine, uses quick-connect fittings, and brings the change to 22 minutes, saving about 56 minutes daily.

Records and checks

  • Record the before and after time for each changeover step and the machine, product pair and date.
  • Verify that the new sequence is written as a one-page standard and posted at the machine.
  • The line supervisor audits the standard monthly, and the plant manager tracks total changeover hours.

Common mistakes

  • Starting with expensive quick-change hardware before first moving simple preparation outside the stop.
  • Skipping the written standard, so each shift does the change its own way and the gain fades.