Spare reorder point
A spare reorder point is the quantity of a spare part at which a fresh order must be placed so that stock does not run out before the delivery arrives.
What it means
It is set by thinking about how fast a spare is used and how long a supplier takes to deliver, with a margin for surprise. For rarely used critical parts the rule differs: hold a minimum of one and reorder the moment it is used.
Example
A plant uses 6 filters a month, and the supplier needs 15 days. Usage during lead time is 3, and with a safety margin of 2 the reorder point is 5: the buyer orders when stock falls to 5.
Records and checks
- Record each spare's reorder point, the usage rate, lead time and the date it was last reviewed.
- Verify stock against the reorder point regularly, and review the level when usage or lead time changes.
- The maintenance supervisor sets the levels; the storekeeper flags items reaching them, and purchase orders them.
Common mistakes
- Setting one blanket level for all spares, whatever their use or lead time.
- Not raising a purchase request when the point is reached, because no one is watching.