Standard cycle time

Standard cycle time is the agreed, normally achievable time for one machine or operator to complete one unit of an operation, used as a reference for planning and costing.

What it means

It comes from timing the operation across several cycles, removing unusual delays and adding a fair allowance for routine interruptions. Planners use it to estimate batch time, and accountants use it for labour and machine cost per piece.

Example

A CNC lathe turns a shaft in 2 minutes 30 seconds. With a standard cycle time of 2.5 minutes, a batch of 600 shafts needs 25 hours of spindle time, plus setup. If actual output is 20 percent slower, the planner can see the gap at once.

Records and checks

  • Record the operation, machine, tooling version, material grade and the timed cycle observations behind the standard.
  • Verify the standard on the floor with a stopwatch or machine log before it goes into planning.
  • The industrial engineer or production head approves it, and the planner reviews it whenever actuals drift.

Common mistakes

  • Setting the standard from the machine's best-ever cycle, which makes every schedule look late.
  • Never revising it after a tool or material change, so planning and costing quietly go wrong.