Takt time
Takt time is the available production time divided by customer demand for the same period, giving the pace at which one unit must be completed to keep up.
What it means
It comes from the German word for rhythm. The calculation uses the time the line actually works, after breaks and planned stops, and the quantity the customers want. If a step takes longer than takt, it cannot keep up; if all steps are much shorter, you have spare capacity. It differs from cycle time, which is how long the work really takes, and the two are compared to see where the line must change.
Example
A Pune plant making 2-wheeler mirrors works 7.5 hours, or 27,000 seconds, a day after breaks. Demand is 900 pairs a day, so takt time is 30 seconds per pair. The assembly step takes 38 seconds, so it must be split, or a second station added, to match demand.
Records and checks
- Record the working time per shift, planned stops, the demand per day and the takt figure.
- Verify demand figures with sales, and recompute takt when shift patterns or demand change.
- The production head sets it; supervisors compare each step's cycle time with it every week.
Common mistakes
- Using the full 8 or 9 hours of attendance, ignoring breaks and meetings, so takt looks too slow.
- Setting it once and never changing it when demand moves over the season.