Variance analysis

Variance analysis is the process of splitting the gap between planned and actual results into its causes, such as price, quantity, efficiency or volume, and acting on them.

What it means

A single total variance does not tell you what went wrong. By splitting it, for example into a price effect and a usage effect for material, you can see whether purchasing, production or the standard itself is the cause. It is done each period, with the biggest variances investigated first, and the findings fed back into the next plan.

Example

A job budgeted 1,000 kg of steel at ₹60, but used 1,080 kg bought at ₹63. The ₹4,800 usage variance came from wastage, and the price rise added ₹3,240. Total adverse variance is ₹8,040, two separate problems for two people.

Records and checks

  • Record the planned and actual price and quantity, the split of the variance and the reason found.
  • Verify the actual quantities against issue slips and the prices against supplier invoices.
  • The cost accountant prepares it, and the managers named for each cause report on corrective action.

Common mistakes

  • Looking only at the total and blaming the department with the visible cost.
  • Investigating every small variance equally, and missing the few large ones.