Plan-to-deliver: exception and recovery register
This register captures every event that breaks the day's plan, and the steps taken to get delivery back on track. Planners, shift supervisors and operations managers use it so that disruption is recorded with its cost and its owner, not just handled by phone. It also shows which disruptions repeat, which tells you where the plan itself is weak.
When to use it
Make an entry as soon as something forces a change to the daily plan: a rush order arrives, an operator is absent, a machine stops, material is late, or two jobs need the same resource at the same time. Fill in the recovery step before the shift ends.
The template
| Exception type | What to record about the effect | First recovery step | Owner | Evidence to attach | Escalate when |
|---|---|---|---|---|---|
| Last-minute rush order | Order, quantity, jobs that will be pushed back | Check free capacity, then accept, refuse or agree a later date | Planner | Demand forecast update, customer message | A pushed-back job has a firm customer date |
| Worker absent | Name, skill missing, hours lost | Move a trained person or reassign work to another shift | Shift supervisor | Attendance, capacity board | Skill cannot be covered for more than a day |
| Equipment unavailable | Machine, expected repair time, jobs affected | Reroute to another machine or outsource the operation | Operations manager | Breakdown note, daily plan | Repair time is unknown |
| Material late or short | Item, shortfall, new arrival date | Substitute, part-ship or reorder by a faster route | Planner | Supplier message, stock count | Substitution needs customer approval |
| Schedule clash | Which jobs, which resource, who decided | Rank the jobs by customer date and move the lower one | Planner | Daily plan before and after | Both jobs have the same firm date |
| Plan not met at end of day | Gap in units or hours, reason | Place the gap in tomorrow's plan, and tell the customer if dates move | Shift supervisor | Progress notes | Gap carries into a third day |
How to fill it
- Exception type: choose the closest line or add one, and reuse the wording so that you can count each type monthly.
- What to record about the effect: units, hours or rupees. "Production loss" is not enough.
- First recovery step: what was done first, not what went wrong.
- Owner: one person who will see it through.
- Evidence to attach: the plan or note that shows the change. Copy the row for each event and add the date logged, case or job number and the next check date.
Example row
| Job | Date logged | Exception | Effect | Recovery step | Owner | Next check |
|---|---|---|---|---|---|---|
| J-218 | 09/11/2026 | Equipment unavailable | Lathe 3 down, 6 machine hours lost, ₹14,400 of jobs delayed | Outsourced 2 hours of turning to a local workshop, remainder moved to Lathe 1 | Operations manager | 10/11/2026 |
Review and sign-off
- The shift supervisor reviews open entries at every huddle, and the operations manager reviews the whole register weekly.
- Close an entry only when the plan is back on track, and write the closing date and what fixed it.
- Escalate to the owner when the same exception type appears three times in a month, or when a firm customer date is lost.
Keeping up to date
- Keep closed registers for the period your CA or the law requires.
- At month end, count entries by type and decide whether to change safety stock, spare capacity or maintenance timing.
- Do not delete old rows. Correct a mistake with a new dated line.