Plan-to-deliver: intake and evidence form

This form opens a planning cycle, usually a week, and gathers the facts the plan rests on. The planner fills it before building the schedule, and the shift supervisor and operations manager add their parts. Having the demand basis, capacity and absences written down in one place means that a missed plan can be traced to a cause instead of argued about afterwards.

When to use it

Fill one in at the start of each planning cycle, before the schedule is published. Use a fresh form when something large changes mid-cycle, such as a big order, a long machine stoppage or a group of workers on leave.

The template

FieldWhat to enterSource recordOwner
Planning period and versionStart and end dates, and a version number such as v1, v2Daily planPlanner
Demand basisWhich orders, forecast lines or appointment bookings the plan covers, and the total quantityDemand forecastPlanner
Capacity requiredHours or units needed for that demand, by team or machineDemand forecast, daily planPlanner
People availableNames or numbers by shift, with known leaveAttendance, leave listShift supervisor
Equipment availableMachines or vehicles in use, and any planned maintenance datesCapacity boardOperations manager
Gap between required and free capacityHours short or spare, and how you will close itCapacity boardOperations manager
Schedule publishedDate and time published, who approved itDaily planOperations manager
Huddle arrangementsTime, place and who leads each shift's huddleHuddle decisionsShift supervisor

How to fill it

  • Planning period and version: a new version for every material change, with the reason. Never overwrite the old one.
  • Demand basis: name the records behind the forecast, such as confirmed orders, last month's dispatches or booked appointments, so that a reader can check it.
  • Capacity required: use the same unit as capacity available, whether hours, units or appointments.
  • People available: record real attendance for the first days and expected attendance after that, and mark which is which. Check the current rule on the official portal or with your CA before acting on any working hours or overtime plan.
  • Gap between required and free capacity: a figure and an action, for example "30 hours short, add Saturday shift".

Example row

FieldEntry
Planning period and version16/11/2026 to 21/11/2026, v2
Demand basis23 confirmed orders, 2,400 units, ₹9,60,000 at selling price
Capacity required310 hours on the packing line
People available12 operators on shift 1, 2 on leave until 18/11/2026
Gap between required and free capacity30 hours short. Add Saturday shift, approve with the owner by 14/11/2026

Review and sign-off

  • The operations manager reviews and signs the form before the schedule is published.
  • Review each form at the end of its cycle, comparing the plan with what was delivered.
  • Escalate to the owner when the gap between required and free capacity is large enough to put a firm customer date at risk.

Keeping up to date

  • Keep every version of the form for the period your CA or the law requires.
  • Add fields for anything that regularly causes surprises, such as festival closures or supplier lead times.
  • Record the date and reason beside each new version so the history is clear.