Plan-to-deliver: role and approval matrix
This matrix sets out who prepares and who approves each planning decision, from the demand forecast to the next-day huddle. Owners and operations managers use it to stop schedules being changed on the shop floor without anyone with authority knowing. Planners and shift supervisors use it to know which changes they can make on their own and which need a second person.
When to use it
Write it when you introduce a formal planning routine, and revisit it when roles change, when a schedule change caused a customer problem, or when a new shift is added. Keep one copy at the planning desk and one with each shift supervisor.
The template
| Decision | Prepared by | Approved by | Proof needed | Cover if approver is absent | If rejected |
|---|---|---|---|---|---|
| Demand forecast for the period | Planner | Shift supervisor | Demand forecast with its source records | Operations manager | Return to the planner with the records to recheck |
| Commit capacity against the forecast | Shift supervisor | Operations manager | Capacity board, attendance | Planner | Reduce the commitment or arrange more capacity |
| Publish the dated schedule | Operations manager | Planner | Daily plan, version number | Shift supervisor | Hold the old plan and fix clashes first |
| Change a published schedule during the day | Shift supervisor | Operations manager | Reason, jobs moved, customer dates affected | Planner | Revert to the published plan |
| Accept a rush order into the plan | Planner | Operations manager | Free capacity shown on the capacity board | Owner | Refuse or offer a later date |
| Approve extra hours or an additional shift | Shift supervisor | Operations manager | Capacity gap, names of people, planned hours | Owner | Re-plan within normal hours |
| Close the day's progress and carry the gap forward | Planner | Shift supervisor | Progress notes, plan against actual | Operations manager | Rework the notes until plan and actual agree |
How to fill it
- Decision: name the event. Add rows for decisions your business makes, such as releasing a job to an outside workshop.
- Prepared by and Approved by: job titles, with different people in each column.
- Proof needed: the record the approver must open. Approval without the record is a signature, not a control.
- Cover if approver is absent: one named person who can approve in their place.
- If rejected: the next step. For extra hours or an additional shift, check the current rule on the official portal or with your CA before acting.
Example row
| Decision | Prepared by | Approved by | Proof needed | If rejected |
|---|---|---|---|---|
| Accept a rush order into the plan | Planner | Operations manager | Capacity board showing 24 free hours on 17/11/2026 against 18 needed for a ₹52,000 order | Offer 20/11/2026 instead |
Review and sign-off
- The owner approves the matrix, signs and dates it, and the operations manager walks each shift supervisor through it.
- Review it every quarter and after any schedule change that went wrong.
- Escalate to the owner when a schedule is found published or changed without the named approver or cover.
Keeping up to date
- Keep each signed version for the period your CA or the law requires, marking older ones as replaced.
- Update the cover column whenever someone goes on leave.
- Record the date each person acknowledges the current version.