Plan-to-deliver: role and approval matrix

This matrix sets out who prepares and who approves each planning decision, from the demand forecast to the next-day huddle. Owners and operations managers use it to stop schedules being changed on the shop floor without anyone with authority knowing. Planners and shift supervisors use it to know which changes they can make on their own and which need a second person.

When to use it

Write it when you introduce a formal planning routine, and revisit it when roles change, when a schedule change caused a customer problem, or when a new shift is added. Keep one copy at the planning desk and one with each shift supervisor.

The template

DecisionPrepared byApproved byProof neededCover if approver is absentIf rejected
Demand forecast for the periodPlannerShift supervisorDemand forecast with its source recordsOperations managerReturn to the planner with the records to recheck
Commit capacity against the forecastShift supervisorOperations managerCapacity board, attendancePlannerReduce the commitment or arrange more capacity
Publish the dated scheduleOperations managerPlannerDaily plan, version numberShift supervisorHold the old plan and fix clashes first
Change a published schedule during the dayShift supervisorOperations managerReason, jobs moved, customer dates affectedPlannerRevert to the published plan
Accept a rush order into the planPlannerOperations managerFree capacity shown on the capacity boardOwnerRefuse or offer a later date
Approve extra hours or an additional shiftShift supervisorOperations managerCapacity gap, names of people, planned hoursOwnerRe-plan within normal hours
Close the day's progress and carry the gap forwardPlannerShift supervisorProgress notes, plan against actualOperations managerRework the notes until plan and actual agree

How to fill it

  • Decision: name the event. Add rows for decisions your business makes, such as releasing a job to an outside workshop.
  • Prepared by and Approved by: job titles, with different people in each column.
  • Proof needed: the record the approver must open. Approval without the record is a signature, not a control.
  • Cover if approver is absent: one named person who can approve in their place.
  • If rejected: the next step. For extra hours or an additional shift, check the current rule on the official portal or with your CA before acting.

Example row

DecisionPrepared byApproved byProof neededIf rejected
Accept a rush order into the planPlannerOperations managerCapacity board showing 24 free hours on 17/11/2026 against 18 needed for a ₹52,000 orderOffer 20/11/2026 instead

Review and sign-off

  • The owner approves the matrix, signs and dates it, and the operations manager walks each shift supervisor through it.
  • Review it every quarter and after any schedule change that went wrong.
  • Escalate to the owner when a schedule is found published or changed without the named approver or cover.

Keeping up to date

  • Keep each signed version for the period your CA or the law requires, marking older ones as replaced.
  • Update the cover column whenever someone goes on leave.
  • Record the date each person acknowledges the current version.
Did not find your answer?Message the lamp team on WhatsApp. Ask about setup, your records, or anything we have not covered here.Ask us on WhatsApp →