Dependency
A dependency is a link between two tasks in a project where one cannot start, or cannot finish, until the other has started or finished.
What it means
The most common kind is finish-to-start: plastering cannot begin until brickwork is done. Others are start-to-start, where two tasks begin together, and finish-to-finish. Dependencies can also be external, such as waiting for a permission, a drawing approval or a delivery. Listing them honestly is what makes a schedule realistic and shows which delays will spread.
Example
In a showroom fit-out, flooring depends on electrical conduit work finishing, and furniture installation depends on flooring being cured for three days. If conduit work slips by four days, flooring and furniture both move.
Records and checks
- Record: predecessor task, successor task, type of link, any lag in days and whether it is internal or external.
- Verify: with the people doing the work that each link is genuine and that none is missing.
- Checked by: the planner updates links when plans change; the project manager reviews them at each weekly meeting.
Common mistakes
- Leaving out external dependencies, such as client approvals, that regularly cause delay.
- Linking tasks "just in case", which makes the schedule longer than needed.