DPR, on a construction or project site, is the usual short form of daily progress report, the dated record of what was done on that day.
What it means
Site teams say "send the DPR" to mean the end-of-day report. In other business settings, DPR can also stand for detailed project report, a long planning document for a new project or loan. The two are quite different, so confirm which one is meant. In day-to-day site work, the DPR is a single sheet, often sent by messaging app or email to the head office by evening.
Example
A supervisor at a road-widening site sends the DPR every day at 6:30 pm: 420 m of subgrade laid, 14 trucks of gravel received, 38 workers present and the roller idle for three hours. Head office compares the figures next morning.
Records and checks
- Record: date, work done by item with quantity, manpower, material received, machines, delays and instructions.
- Verify: that the numbers agree with site measurements and the previous day's balance.
- Checked by: the site engineer reviews and signs; head office reviews trends weekly.
Common mistakes
- Using DPR for two meanings in the same team without saying which.
- Reporting percentages complete with no quantities behind them.