Extrusion rate
Extrusion rate is the quantity of product an extruder delivers per unit of time, usually stated in kilograms per hour or metres per minute.
What it means
It is the main measure of an extruder's productivity. The rate depends on screw speed, screw design, material, die and the cooling and pulling arrangement behind it. Running faster raises output but can raise melt temperature and spoil quality, so the practical rate is the highest one that still gives good product. It is used for planning job times, power per kilogram and the cost per metre.
Example
A film line is rated at 80 kg an hour. For a job of 2,400 kg of 30-micron film, the planner allows 30 hours of running, plus setup. Measured over a shift, the line actually delivers 72 kg an hour, so the plan is corrected to 33 hours before the delivery promise is made.
Records and checks
- Record the kilograms or metres produced against run hours, with the product, die and screw speed.
- Verify the rate by weighing output over a fixed time, not by trusting the machine display.
- The operator records the output, the supervisor compares it with the standard rate, and the planner uses the actual rate.
Common mistakes
- Planning with the rated figure from the machine brochure instead of the rate actually achieved.
- Chasing a higher rate with higher screw speed until the film or pipe quality falls.