Machine loading

Machine loading is the assignment of jobs to specific machines and the comparison of total booked hours with the hours each machine has available.

What it means

It answers which machine will do which job and how full each machine will be. The planner adds up the run and setup hours of all jobs given to a machine, and compares this with available hours after breaks and maintenance. A load above 100 per cent shows a problem to solve now, while a low load on some machines shows spare capacity that could take work from the overloaded ones.

Example

A Pune plastics unit has four injection moulding machines with 150 available hours each next week. Machine 2 is loaded with 172 hours of jobs and Machine 4 with 90. The planner moves one 25-hour mould that fits both to Machine 4, so loads are 147 and 115 hours, and no job has to wait.

Records and checks

  • Record each machine's available hours, jobs assigned, hours booked and the load percentage.
  • Verify that jobs are only assigned to machines able to run them, by tonnage, size and tooling.
  • The production planner prepares it; the plant manager reviews it before it goes to the shop floor.

Common mistakes

  • Moving a job to a free machine that cannot actually run it, discovering the problem at setup.
  • Ignoring setup time, so a machine with many short jobs looks lightly loaded when it is not.