lamp.
ResourcesPricingAbout

Machine setup

Machine setup is all the work done to prepare a machine for a new job, such as fitting tools and fixtures, loading programs, adjusting settings and running trial pieces.

What it means

During setup the machine makes no saleable output, so its cost is spread over the pieces in the batch. Short batches carry a larger setup cost per piece. Setup time runs from the last good piece of the previous job to the first good piece of the new one. Planning job sequences and preparing tools while the machine still runs reduces it.

Example

A milling machine needs 90 minutes to change fixtures, load a program and prove the first piece. At ₹300 per machine hour, setup costs ₹450: ₹9 per piece on a batch of 50, but only 45 paise on a batch of 1,000.

Records and checks

  • Record setup start, finish, job, machine, operator and trial pieces used.
  • Verify that setup time is booked separately from run time and idle time.
  • The supervisor signs the setup sheet; the planner reviews setup times when sequencing jobs.

Common mistakes

  • Mixing setup time into run time, so the true cost of small batches is never seen.
  • Ordering jobs without thinking of similar tooling, causing avoidable changeovers.
Did not find your answer?Message the lamp team on WhatsApp. Ask about setup, your records, or anything we have not covered here.Ask us on WhatsApp →