Master production schedule
The master production schedule is the plan of which finished products, in what quantities, will be completed in each time period, from which material and capacity needs are worked out.
What it means
It sits between the sales forecast and detailed shop-floor planning. It takes confirmed orders and forecast demand, considers stock and capacity, and sets how many of each end item will be finished each week. Because everything else follows from it, a near-term section is usually kept steady, and changes inside it need approval. Without it, purchasing and production react to each day's orders.
Example
A Bengaluru maker of weighing scales has orders for 340 units and a forecast of 200 more in March. With 90 in stock and capacity for 100 a week, it schedules 100, 100, 120 and 90 units over four weeks, and freezes the first two weeks from changes except with the plant head's approval.
Records and checks
- Record each end item, the quantity and week, the orders and forecast it covers and its revision date.
- Verify that the total is within capacity and that the schedule matches confirmed customer commitments.
- The planning head prepares it; sales and production agree it in a weekly meeting.
Common mistakes
- Changing the near-term schedule for every rush order, which unsettles purchasing and the shop floor.
- Scheduling to forecast without netting existing stock, so excess goods pile up.