Material reconciliation

Material reconciliation is the comparison of material issued to a job against the amount the completed work should have consumed and the stock remaining, to find wastage, loss or errors.

What it means

You start with the quantity issued, subtract the theoretical consumption calculated from measured work and the balance in hand, and examine any difference. Some wastage is expected and allowed, for instance 3 per cent on tiles. Anything beyond is queried. Done periodically, it exposes theft, over-ordering and quality rejection while there is still time to act.

Example

A contractor is issued 6 tonnes of steel for a slab. Drawings show the work needs 5.4 tonnes, 0.25 tonne remains in stock and 0.1 tonne is wastage within limits. The missing 0.25 tonne is flagged and traced to steel given to another site.

Records and checks

  • Record: opening stock, material issued, quantity used per measurement, allowed wastage, scrap and closing stock.
  • Verify: physical stock on site against the book balance and the consumption against drawings.
  • Checked by: the storekeeper prepares it; the site engineer explains variances; the project head approves.

Common mistakes

  • Reconciling only at the end of the project when materials are already gone.
  • Using a generous wastage allowance that hides real loss.