Material requirement

A material requirement is the quantity of a material needed for a specified job or period, calculated from the parts list, wastage allowance and stock already held.

What it means

It is the starting point for purchasing. For a job, you multiply the quantity per unit by the number of units, add an allowance for scrap and cutting loss, and then subtract what is already in stock or on order. What remains is the net requirement to be bought. Getting it right avoids both a mid-job stoppage and surplus material that sits on the shelf for years.

Example

A Nashik fabricator must make 40 water tanks, each using 14 sq m of 2 mm stainless sheet, with 8 per cent cutting loss. Gross need is 40 times 14 times 1.08, about 605 sq m. Stores has 150 sq m and 100 sq m is on order, so the net requirement to purchase is about 355 sq m.

Records and checks

  • Record the job, item, quantity per unit, wastage allowance, stock, open orders and net need.
  • Verify the wastage allowance against actual scrap from past jobs.
  • The planner or store keeper calculates it; the buyer confirms before ordering.

Common mistakes

  • Forgetting the cutting loss, so the job runs short by a few tanks.
  • Ignoring material on order, so the same need is purchased twice.