Material requirements planning
Material requirements planning is a method that calculates what materials and components are needed, in what quantity and by when, from the production schedule, parts lists and current stock.
What it means
It starts with how many finished products are to be made and when. It then explodes each product's bill of materials into parts, subtracts what is in stock or already ordered, and moves the need back in time by the lead time of each part. The output is a list of what to order or make and by what date. It prevents both shortages that stop production and excess stock that ties up cash.
Example
A Pune bicycle assembler plans 500 bicycles for week 6. Each needs one frame, two wheels and one chain set. Stock holds 120 frames, 200 wheels and 80 chain sets, with 100 wheels already on order. The plan calls for 380 frames, 700 wheels, 420 chain sets, each placed earlier by its supplier lead time.
Records and checks
- Record the schedule, parts lists, stock, open orders, lead times and the resulting suggested orders.
- Verify the stock and lead time values, because errors in them flow directly to the plan.
- The planner or purchaser runs it; the purchase head reviews suggestions before orders are placed.
Common mistakes
- Running it on inaccurate stock records, so shortages and excess are both wrongly shown.
- Using supplier lead times from years ago, so parts arrive late despite a correct plan.